Eastern Kentucky’s largest retail utility is asking state regulators for permission to build a gas-fired power plant in Lawrence County to supply electricity to a planned hyperscale data center.
Kentucky Power, an Ashland-based utility serving 20 counties in eastern Kentucky, is seeking approval from the Kentucky Public Service Commission to build a new natural gas plant next door to its Big Sandy natural gas power plant near Louisa. The utility announced its plans on Nov. 13.
In a news release, Kentucky Power says it wants the new power plant to meet the electricity demands of the Muskie Data Campus, a hyperscale data center planned for the EastPark Industrial Park in Grayson. TeraWulf, the developer behind the data center, requires 1 gigawatt of electricity to power the data center. The proposed power plant would have a generating capacity of 769 megawatts.
According to Kentucky Power’s filing, the data center project would require more than $3 billion in investment to build the necessary power generation and transmission infrastructure. The estimated cost is approximately $2.81 billion for the power plant build-out and $285 million for the proposed Venator transmission substation.
If approved, TeraWulf said it will fund $100 million in winter-bill credits for Kentucky Power customers beginning in 2029. The credits would provide residential customers with approximately $25 in monthly savings during the winter heating season for 10 years.
“Our commitment to eastern Kentucky goes beyond providing reliable electricity. We’ve served these communities for generations, and we want our customers and communities to share directly in the benefits when new investment comes to the region,” Kentucky Power President Cindy Wiseman said in the release. “Eastern Kentucky has a tremendous opportunity ahead, and thoughtful growth can strengthen our electric system, support good jobs and attract new investment.”
Electricity bills are typically higher during winter months, as colder outdoor temperatures place greater strain on a home’s heat pumps. Moreover, the rapid expansion of data centers has raised concerns about whether the infrastructure needed to meet their electricity demand could increase costs for existing utility customers.
The Big Sandy Power Plant has been a key cog in eastern Kentucky’s electrical infrastructure since opening in 1963. Established as a coal-fired facility, the plant was converted to natural gas in 2016 to reduce operating costs and greenhouse gas emissions.
TeraWulf is actively developing another hyperscale data center in Hancock County, on the site of a shuttered aluminum smelting plant, for A.I. giant Anthropic.